Saturday, 30 July 2022

Memories of Rehabilitation of British-Era Jabban Hydropower Project in Malakand KPK

2012 to 2014

Habib Rafiq (Pvt.) Limited is one of the biggest construction companies in Pakistan. I joined them in 2012, and one of my assignments as a civil engineer was Jabban Hydropower Construction. 

To meet the requirements of irrigation in Malakand valley and districts of Mardan and Swabi, an irrigation scheme was planned by the British Government in 1903. The plan consists of headwork at Amandara near Batkhela on River upper Swat, unlined irrigation channel 7.2 Km long up to Malakand Pass, and excavation of 17.5 Ft dia, 3.4 Km long tunnel underneath of Malakand Pass. A network of irrigation canals including Abazi and Machai branches and their distributaries were also part of the project. The project started in 1907 and was completed in 1914.

In 1930, a hydropower project was planned by the British Government, at Jabban, 10 Km from Dargai town Malakand Agency. For this purpose, a free power tunnel called Barkat tunnel was excavated on the right side of the outlet regulator of the Benton tunnel. The length of the tunnel is 0.97 Km and its diameter is about 14 feet. The discharge capacity of Barkit tunnel is 1200 cusecs. Jabban hydropower projects were started in 1934 and completed in 1937.

The 70-year-old powerhouse was badly damaged due to a fire incident on 12-11-2006. The extent of damage was such that it was not possible to restore the operation of the existing units. Moreover, the plant equipment had already outlived its life. The situation necessitated carrying out Rehabilitation of Jabban Hydroelectric Power Station on a "Fast Track Basis" by the installation of new machines of higher efficiency at the same site.

The Rehabilitation of the hydropower station was completed in 2013 with a total cost of Rs3.8 billion by the contractor HRL-CCPG JV (Habib Rafique Ltd. (Pakistan) & Central China Power Group China).

Since its commissioning in 1937 with an initial installed capacity of 9.6 MW (3 units of 3.2 MW each).

Jabban Hydropower after completion 2014


Turbine Building

Channel to feed Forebays

3.4 Km long tunnel canal underneath of Malakand Pass


To reach the forebay a rail line was installed in British times. 

From the initial 9 Megawatta capacity after rehabilitation, the new Generation capacity we got is 23 MW. We have to increase the Pipe opening at Forebay which feeds the turbine

Standing at Forebay Deck

View from Forebay, opening for turbine foundation is in process

3.4 Km long tunnel canal underneath of Malakand Pass



























1 comment:

  1. Your way of description about building house in India is rally very authentic. Thanks for sharing. Please keep sharing.
    sale luxury villa in pakistan

    ReplyDelete